STEEL WORKS

Lifting of 45m span truss. Weight 9.5 ton. Height 15meters

Assembly of Main beams and bracings

Side wall installed

Lifting of 45m span truss. Weight 9.5 ton. Height 15meters
45 meter free span truss clay storage roof coverage Alexandria Cement Plant (Titan)

Overview of main stack

Overview of installation area 2nd floor

Insulation

Overview of main stack
Connection of Main and Bypass Stacks
Ein Sokhna - Arabian Cement Company

Unloading

Relocation to site

Extension Platform done view from ground level

Unloading
Extension Platform
Ein Sokhna - Arabian Cement Company

Tank workshop assembly completed

Sandblasting

Finishing

Tank workshop assembly completed
Design, fabrication and installation Ammonia Steel Tank-Lesaffre Plant Nubareyah
ELECTRO-MECHANICAL INSTALLATION

RDF Site

Unloading of 40 ton Shredder

Operation

RDF Site
Installation of 40 ton RDF shredder
Abis Plant (Titan)

Supporting structure adjustment

Dedusting piping

Supporting structure adjustment
Coal Vacuum Cleaner
Alexandria Cement Plant (Titan)

Improper sealing around duct, duct capacity insufficient (overheating)

View of existing duct from outside room

Installation complete

Improper sealing around duct, duct capacity insufficient (overheating)
Compressor room ventialation system modification
Extension Platform
Ein Sokhna - Arabian Cement Company

Start of Extension Project

RDF Site

Cable Routing

Start of Extension Project
Turnkey RDF Sorting Plant Extension
Sannour Plant (Titan)
MAINTENANCE

Shop-fabriated parts in site

Site assembly of shop-fabricated parts

Goose Neck ready for lifting

Shop-fabriated parts in site
Replacement of Raw Mill Elbow Duct
Amreyah Cement Company

Damaged concrete

Damaged concrete and steel coverage

Covering for columns

Damaged concrete